XIII. SPECIFIC SITES
XIII. Specific Sites- Planning Factors
A. Type of Site....................................................... []
1. Raw land, previously undeveloped............................... []
2. Zoned office/industrial but not in planned park................ []
3. Planned office or industrial park.............................. []
4. Urban, suburban, rural......................................... []
5. Waterfront or airport frontage................................. []
6. Redevelopment area............................................. []
7. Drained or reclaimed land...................................... []
8. Cleared, graded land........................................... []
9. Site in large-scale PUD or new town............................ []
10. Previous land use, toxic waste risk............................ []
11. Adjacent land use.............................................. []
B. Topographic Consideration.......................................... []
1. Slope and grade................................................ []
2. Potential aesthetic problems................................... []
3. Legislation restricting construction due to topography......... []
4. Height above sea level......................................... []
5. "Look window" for satellite antenna....
C. Geologic Consideration............................................. []
1. Depth of solid rock and character or intervening soil strata... []
2. Bearing loads as compared with requirements.................... []
3. Soil analysis.................................................. []
4. Variation in ground water level................................ []
5. Flood risk and flood plains of surface bodies of water......... []
6. Drainage pattern after plant construction...................... []
7. Earthquake risk................................................ []
D. Transportation Service on Site (See also "Transportation")......... []
1. Airport at site................................................ []
2. Taxiway access to plant sites.................................. []
3. Rail siding.................................................... []
4. Truck dock..................................................... []
5. Deepwater dock................................................. []
6. Barge dock..................................................... []
7. Rapid transit stop............................................. []
8. Streets........................................................ []
E. Transportation Service in Area..................................... []
1. Approximate miles to closest Interstate highway access......... []
2. Approximate miles to closest air carrier airport............... []
3. Approximate miles to closest general aviation airport.......... []
4. Approximate miles to closest deepwater port.................... []
5. Approximate distance to main rail-line......................... []
F. Potential for Intermodal Transfer of Containers.................... []
1. Rail-truck..................................................... []
2. Air-truck...................................................... []
3. Ship-truck..................................................... []
4. Rail-ship...................................................... []
5. Rail-air....................................................... []
6. Ship-air....................................................... []
7. Barge-rail..................................................... []
8. Barge-truck.................................................... []
9. Barge-air...................................................... []
G. Utilities (See "Power and Fuel," "Water and Waste Disposal")....... []
H. Site development costs............................................. []
1. Cost of water line, who pays................................... []
2. Cost of sewer line, who pays................................... []
3. Cost of electric line, who pays................................ []
4. Cost of rail line, who pays.................................... []
5. Cost of access road, who pays.................................. []
6. Clearing and grading cost...................................... []
I. Intangible Considerations.......................................... []
1. Natural surroundings........................................... []
2. Advertising value of site...................................... []
3. View of building from distance and view from within building... []
4. Neighbors...................................................... []
5. Security....................................................... []
J. Legal Check-Points................................................. []
1. Title.......................................................... []
2. Easements...................................................... []
3. Protective covenants, deed restrictions........................ []
4. Abandoned cemeteries........................................... []
5. Mineral rights................................................. []
6. If site is in multiple ownership............................... []
a) Get accurate list of present owners........................ []
b) Develop profile on each owner.............................. []
c) Determine reasons for present use.......................... []
d) Obtain expert opinion on current market value.............. []
e) Be prepared to risk option money........................... []
f) Use "straw man" for contacts, perhaps your law firm........ []
K. Cost of Land....................................................... []
1. Initial cost, assuming options obtained without publicity...... []
2. Cost if project is publicized.................................. []
3. Broker fees.................................................... []
4. Probable appreciation of land value............................ []
L. Zoning Requirements................................................ []
1. Uses permitted................................................. []
2. Off-street parking............................................. []
3. Set-backs...................................................... []
4. Percent of site that may be utilized........................... []
5. Control of nuisances (smoke, dust, noise,etc.)................. []
6. Sign control................................................... []
7. Height restrictions............................................ []
M. Consideration of Special Strategies................................ []
1. Purchase of site large enough for more than one plant, setting up
a "site bank" for future use................................... []
2. Use of surplus corporate property, including available land and
buildings...................................................... []
3. Developing own industrial park or complex and locating plant in it,
thus capturing some of own economic impact..................... []
4. Swapping company property elsewhere for site to avoid tax con-
sequences...................................................... []
5. Leasehold on public land, such as an airport or urban renewal
area........................................................... []
6. Site on closed military base, to use existing facilities, employ
skilled workers, etc........................................... []
7. Establish a plant under the twin plant concept (unit outside the
U.S. furnishing assemblies to unit in the U.S.)................ []
N. Deed Covenants (presented according to IDRC Uniform Outline)....... []
i. Introductory Section........................................... []
1. Purpose.................................................... []
2. Ownership.................................................. []
3. Definitions................................................ []
ii. Land-Use Criteria.............................................. []
1. Allowable land-use......................................... []
2. Prohibited land-use........................................ []
3. Special uses............................................... []
iii. Performance Standards (except local, state, federal environmental
regulations)................................................... []
1. Noise...................................................... []
2. Fire and explosives........................................ []
3. Vibration or shock......................................... []
4. Smoke or heat.............................................. []
5. Illumination or glare...................................... []
6. Particulate matter, dust and dirt.......................... []
7. Electrical disturbances.................................... []
8. Odors, toxic and noxious matter............................ []
9. Drainage................................................... []
10. Excavations................................................ []
11. Radiation.................................................. []
iv. Space Allocations and Dimensional Standards.................... []
1. Building-to-land ratio..................................... []
Minimum building size...................................... []
Minimum lot size........................................... []
2. Set-backs- front yard...................................... []
3. Set-backs- side yard....................................... []
4. Set-backs- rear yard....................................... []
5. Exceptions to side yard and rear yard limits............... []
6. Rail siding................................................ []
7. Height limitations......................................... []
Allowable variations....................................... []
8. Off-street parking areas................................... []
9. Off-street loading areas................................... []
10. Easements and rights-of-way................................ []
11. Streets and driveways...................................... []
12. Sidewalks and curbing...................................... []
v. Architectural and Aesthetic Standards.......................... []
1. Landscaping and limitations on cutting natural growth...... []
2. Exterior construction, permitted materials, prohibited
materials, approved construction methods................... []
3. Signs...................................................... []
4. Outdoor storage............................................ []
5. Maintenance requirements, refuse collection and prohibition of
junk storage............................................... []
6. Utilities placement and design............................. []
vi. Implementation of Plans and Construction....................... []
1. Architectural review and approval of building plans-
procedure.................................................. []
2. Extension to include additional property................... []
3. Developers right to alter or change covenants.............. []
4. Enforcement................................................ []
5. Fees....................................................... []
6. Property owners association................................ []
7. Repurchase rights.......................................... []
8. Separability............................................... []
9. Termination and modifications.............................. []
10. Constructive notice and acceptance......................... []
11. Completion of construction, temporary structures........... []
12. Miscellaneous.............................................. []
vii. Special Provisions Peculiar to Project or Site................. []
[Next Page]|
[Return to Checklist]|
[Home page]
Copyright 1995 Conway Data, Inc. All rights reserved
Legal Notice: Because data comes from many sources, Conway Data
can assume no responsibility for accuracy or currency.