Permits, Right-of-Way, and Utilities
Alameda Corridor Transportation Authority
- Environmental Impact Statement/Environmental Impact Report completed
- No other major environmental approvals required
- Contractor obligated to obtain permits
- Corridor Cities have agreed to expedite permits
Right-of-Way and Utilities
- 95% of right-of-way already obtained
- Schedule for obtaining remaining parcels (condemnation)
- Master Agreements with utility owners (including cities) regarding relocations; major longitudinal encroachments will all be removed by mid-1999
- Contractor has primary responsibility to ensure that relocations occur
Substantial progress has been made in securing permits, purchasing right-of-way, and relocating utilities